05:04 pm MIWP-Action #2909: 2016.5: Priority list of data sets for eReporting

 Short debrief of the progress in 2016.5 task since December 2017

 - Presentation of 2016.5 status at th...

Jose Miguel Rubio Iglesias
02:27 pm MIWP-Action #2870 (Closed): 2016.2: Streamlining the monitoring and reporting for 2019

Michael Lutz
02:26 pm MIWP-Action #2870: 2016.2: Streamlining the monitoring and reporting for 2019

The action was formally closed in the MIG meeting in June 2017.

Michael Lutz
02:26 pm MIWP-Action #2127 (Closed): 2016.3: Validation and conformity testing (previously MIWP-5)

The action was formally closed in the MIG meeting in June 2017.

Michael Lutz
02:13 pm MIWP-Action #3083 (New): 2017.4: Validation and conformity testing

This issue is used to track progress of action 2017.4, according to the following schema.

Progress since the la...

Michael Lutz
02:12 pm MIWP-Action #3082 (New): 2017.3: Improved client support for INSPIRE data

This issue is used to track progress of action 2017.3, according to the following schema.

Progress since the la...

Michael Lutz
02:11 pm MIWP-Action #3081 (New): 2017.2: Alternative encodings for INSPIRE data

This issue is used to track progress of action 2017.2, according to the following schema.

Progress since the la...

Michael Lutz
02:10 pm MIWP-Action #3080 (New): 2017.1: Drafting of "Master Guidelines" for the INSPIRE directive

This issue is used to track progress of action 2017.1, according to the following schema.

Progress since the la...